Watch this video to see how we use our proprietary composite arch tubes to revolutionize bridge construction.

The McGee Bridge was completed in August 2009. The bridge took 12 working days, including demolition of the existing bridge and all the site work. Construction finished ahead of schedule with a crew of five and no heavy equipment, just a mid-sized excavator. We applied knowledge gained from the Neal Bridge project to optimize an efficient design, enabling us to bid lower than every concrete, steel and wood alternative.