2019

Wyalusing, PA

Owner
Engineer

AIT's Miter End

New Fortress Energy

Black & Veatch Construction, Inc.

Overland Park, KS

Trumbull Energy Services

Contractor
Span
Rise
Width
Skew
Headwall
About
Arches

29'

6'

103'

AIT's first Mitered end eliminates the cost of headwalls and accelerates construction, from concept to project completion in 8 months. Designed to carry loads of 1.5 million lbs, Overcame unique foundation conditions due to heavy rains.

15 Full Glass Fiber Tubes, 3 Partial Glass Fiber Tubes, 5'-6" spacing, 12" diameter

Wyalusing Bridge